An in-situ chemical oxidation (ISCO) remediation was conducted at a former wellsite sump in Barrhead, Alberta to address BTEX, F1, and F2 contamination in 645 m³ of impacted soil and 3,000 m³ of impacted groundwater. Due to shallow groundwater and a saturated silty sand lithology, excavation was limited, requiring targeted in-situ treatment. A 0.75-meter injection radius was used for soil treatment via 40 injection points, delivering 28,000 liters of 10-15% MFR (modified Fenton’s reagent) over five days, while groundwater remediation involved 13 wells, injecting 60,000 liters over two events spanning 20 days. Using TRIUM’s TriOx process, the project achieved a >90% contaminant reduction, meeting regulatory guidelines within a short treatment timeframe.
Former admixed drilling sump at an abandoned wellsite. Surficial soil impacts were excavated and removed from Site. Shallow groundwater limited excavation and required in-situ treatment method for remaining soil impacts and groundwater impacts. Lithology of the target treatment zone is saturated silty sand, creating a pathway for contaminant migration.
In-situ chemical oxidation (ISCO) program based on treatment of soils using drive points on a 0.75 meter injection radius of influence to increase contact certainty between the oxidant and contaminants due to unsaturated soils. Groundwater injections were completed using 13 injection wells targeting the saturated intervals. Injections were completed in the fall and winter so as to have a frost cap in winter.
The soil treatment program was conducted over 5 days with the advancement of 40 injection points and 28,000 litres of blended 10-15% MFR (modified fentons reagent) oxidant injected. The groundwater treatment program was conducted over 2 events for a total of 20 days and injection in 13 injection points and 60,000 litres of blended 10-15% MFR (modified fentons reagent) oxidant injected. Blending is site specific following TRIUM’s TriOx process.
An in-situ chemical oxidation (ISCO) remediation was conducted at a residential property in North Vancouver to address petroleum hydrocarbons (LEPH), phenanthrene, and pyrene contamination in 200 m³ of impacted soil and groundwater following a heating oil UST leak that migrated under the building foundation, causing vapour intrusion and free product in property sumps. A 2.5-meter injection radius was used for targeted treatments within the basement and exterior property foundation, utilizing directional injections and drive-points to reach both saturated and unsaturated zones. TRIUM leveraged the property’s sump system to artificially raise the groundwater level, creating a fully saturated treatment zone. Over seven days, 24 basement injections and 3 exterior injections delivered 20,104 litres of sodium persulfate, blended using TRIUM’s TriOx process with specialized activation products. The treatment successfully met regulatory soil, groundwater, and vapour guidelines, required only six weeks for completion, and allowed the property owner to safely return home with minimal disturbance.
A pipeline release at an active multi-well pad in Central Alberta required remediation due to BTEX, F1, F2, and PAH contamination in 2,000 m³ of impacted soil and groundwater, with remediation timeframes limited by site conditions. A staged risk-based in-situ chemical oxidation (ISCO) approach was implemented with a 3-meter injection radius, involving the installation of 52 injection wells and five permeable reaction trenches to facilitate groundwater extraction and oxidant circulation. A total of 17,500 liters of 12% EHP (enhanced hydrogen peroxide) was injected using TRIUM’s ChemOx® process, with injections timed during frost-cap months to maintain pressure. Results show a well-defined and shrinking plume, significant source area concentration reductions, and an approximate 90% decrease in PHC and PAH concentrations since project inception.